PROJECT:
To construct a services access road through a swampy area for Country Energy Contractor vehicles.
LOCATION:
Marom Creek Road, MEERSCHAUM VALE NSW
PROJECT STATS:
- 36 square metres –
- 1 roll – 2.4m wide x 15m mat
- 1.5 hour start to finish
- 1 5 ton excavator with bucket
- 1 operator and 1 labourer

PROJECT OVERVIEW
Farm creek crossing and culvert entrance was dry due to drought so prime opportunity to clear out and construct a suitable hard surface access road for services to driveover without getting bogged and to avoide further erosion of the creek bed from fast flowing water.
WORKS UNDERTAKEN
- Excavator was used to clear debris and weeds along the creek and culvert opening and stabilise the base of the creek bed.
- Area was seeded for grass to grow under the mat
- Concrete Erosion rolls placed into position and unrolled into place
- The flexible nature of the mats ensured that it easily contoured to the curves of the creek bed.
- The bucket of the loader simply pulled the mat to straighten and into position
- Once the mat was in position the excavator drove over it to track the mat into the ground
RESULTS & BENEFITS:
- Reduce the velocity of the water when it flowed across the concrete mat
- Vegetation will grow through the mat and allow for the farmer to maintain into the future
- Reduce sediment loss and maintain a hard surface creek crossing
- Very efficient with time and resources.
- The works were completed swiftly, with minimal labour and effort
- Once laid the mats start working straight away.



GALLERY OF WORKS
ACM Project – Temporary Boat Ramp – DIngo Beach QLD
PROJECT: Build Temporary Boat Ramp for access alongside the construction of permanent ramp LOCATION: DINGO BEACH near...
ACM Project – Orchard Water Channel – Alstonvale NSW 2477
PROJECT: Cleanup and protection of Macadamia orchard water channel and drain LOCATION: Sneaths Lane, ALSTONVALE NSW...
ACM Project – Roadside Swale Drain – Alstonvale NSW
PROJECT: Farm access road required roadside drains to be cleaned up and protected from further erosion. Concrete...
ACM Project – Dam Spillway and Overflow Channel – Meerschaum Vale NSW
PROJECT: To construct a spillway and overflow channel to control the release of flows from the farm dam LOCATION:...
ACM Project – Roadside Swale Drain – Beaudesert QLD
PROJECT: Concrete Erosion Mats were applied to swale drains along the edges of a newly constructed road and bridge....
ACM Project – Farm Water Channel and Drain Clean Up – Dungarubba NSW
PROJECT: Cleanup and Protection of drain outlet and water channel on Sugarcane Farm LOCATION: DUNGARUBBA, New South...